|
|
|
The pictures and descriptions provided below represent a sample of some of the projects that the company's engineers have worked on. For further information, contact one of the principal engineers by phone or email using the contact information contained in the Contact Info page. To view full size pictures click on the thumbnail. A listing of additional projects is included at the bottom of the page. Relay Panels
PLC Panels
Substation Projects
Line Design
Supervisory Control and Data Acquisition (SCADA) Systems
Engineering Studies
Transformer Failure Analysis & Protection Addition
Power Quality Metering System
Additional Projects
Substation
Projects Foxhill 230-34.5 kV Substation, Stroudsburg, PA
- This
project entailed the construction of a new 230-34.5 kV distribution substation.
The various protective schemes included in the project were: 1) Redundant
Fiber optic Current Differential protection scheme for bus tie protection, 2)
Redundant Directional Comparison Blocking protection on the 230 kV line feeding
the station, and 3) Transformer and distribution line protection.
In addition to performing the short circuit analysis and specification
and coordination of protective devices, completed the control circuit design
used in the substation. Lorane
#1 Bk Replacement Project, Reading, PA
- This
project included the replacement of an existing 14 MVA 69-13.2 kV transformer
with a new 28 MVA 69-13.2 kV unit. Protection
schemes upgraded as part of this project included new transformer differential
protection, as well as, microprocessor based transformer overload and
distribution feeder protection. Glendon 115 kV Rebuild Project, Easton, PA
- This
project included the replacement of 115 kV line protection at six (6) terminals
and transformer protection for two (2) 115-34.5 kV transformers.
Determined the protective relay schemes to be installed, as well as, the
settings for all of the relays. Completed
the control scheme design and assisted the technicians in commissioning and
testing the new schemes. Warren 230 kV Substation Project, Warren, PA
- This
project entailed the installation of a new 230 kV breaker terminal, 230-115 kV
auto-transformer, and relay replacements at two (2) remote 230 kV terminals.
Responsibilities included substation expansion, specifying equipment,
protection and control design, determining all of the relay settings and
supervising the commissioning and in-service testing of the equipment installed.
Developed test plans and provided training for the technicians on the
testing of all relays. Tower Hill 115-34.5 kV Substation Project, Mansfield, PA
- This
project included the installation of a new 115 kV terminal at an existing
substation and the construction of a new 115-34.5 kV Substation.
Completed the substation design and protection scheme design, including
panel layout and wiring design. Determined
all of the relay settings necessary. The
substation protection was performed almost exclusively with microprocessor-based
relays. Provided training and
supervision for the commissioning and in-service testing of all of the equipment
installed. Pleasureville
983 Line Terminal Project, York, PA This
project entailed the engineering required for the addition of a 115 kV line
terminal at the Pleasureville Substation. Project
design included the design of a new 115 kV terminal including box structure
addition, new circuit breaker, new line protection panel utilizing a directional
comparison blocking scheme using power line carrier equipment.
Developed all of the relay settings required for the project. East
Sayre Relay Replacement Project, Sayre, PA
Completed the design of a new 115 kV line
protection panel to replace and existing electromechanical relay panel.
Also, developed all relay settings required for the project.
Project management activities included coordination with an
interconnecting utility and their customer on meeting the project schedule and
requirements. Westgate
Substation, York, PA Project
engineer for the $1.2 million addition of a new 115 kV 13.2 kV substation
with 2 - 115 kV breakers, a 28 MVA transformer, and 13.2 kV switchgear. Hunterstown Substation, Gettysburg, PA Project
was to add a new 500kV shunt capacitor bank recommended by the power pool to
increase power transfers from west to east.
This included a 500kV capacitor bank and an associated 500kV circuit
breaker. This also included a
programmable logic controller to automatically switch the capacitor breaker for
system conditions that require the capacitor to be tied to the system.
Responsibility for this project was substation design, protection, and control
design, and relay settings. Northwood
Substation, Forks Twsp, PA
This project
was to determine the failure mode of two 230kV 34.5kV, 125 MVA transformers,
specify and manage the purchase and design of a new replacement transformer, and
to specify and manage the repair of the second failed transformer.
Responsibility for this project was to analyze all operation and failure
data to determine what caused the failures and specify the design requirements
for a new transformer. Responsibility also included following the transformer
through design, performing the transformer core and coil inspections, overseeing
the final testing, and providing field direction for the installation.
The requirements of the project also included overseeing the disassembly
of the second failed unit and working with the manufacturer that was redesigning
the unit to assure all our requirements were met. Yorkana Substation, York, PA
Project scope was to add a second 230kV 115kV
200MVA autotransformer to the existing substation.
Project responsibility included, specifying and managing the purchase and
design of the new transformer, complete all substation upgrades, determine the
relay schemes required, complete all control design, perform fault analysis, and
complete all relay settings. Erie South 230kV Shunt Capacitor Bank
Installation, Erie, PA Responsible
for installation, testing, and commissioning for the addition of two (2) 65MVAR
substation shunt capacitor banks. This
included major modifications to the 230kV bus and the relay protection.
Scheduled 230kV bus outages, coordinated construction and testing crews,
planned the work in stages to allow for only short outages of the 230kV bus to
tie in major systems. Also
responsible for preparing as-built drawings for the project. East Windsor 500kV substation
expansion, Windsor, NJ Project
Manager for the design, installation,
and testing of a second 500kV 230kV, three phase, 870MVA transformer and
230kV ring bus at Jersey Central Power & Lights East Windsor substation.
This project also included 500kV line re-routing including a new double
circuit 500kV tubular steel pole design, and 230kV line re-routing. United Coorstack,
Reading, PA This
project included replacing a failed 69kV 13.8kV, 14MVA transformer,
upgrading transformer protection, performing a lightning and insulation
coordination study, performing a relay coordination study, relay settings, and
adding power quality metering to the substation.
Construction specification and coordination was also provided. Fairchild
Semiconductor, Mountain Top, PA Designed
and commissioned the installation of a SCADA system to gather transformer and
feeder load and status information from the substation and send it to their
plant control system. Generation
Projects Portland Unit #5 Combustion Turbine Project, Portland, PA
- Reviewed/specified
and determined settings for all of the protective relaying equipment used to
protect the 150 MVA generator and associated equipment.
Also, was assigned the responsibility for commissioning this equipment
during the period between July and November of 1994.
Developed a test program and scheduled and supervised the contractors
hired to do the testing. In addition, worked closely with the manufacturer's
commissioning engineers during the "Primary Test" phase of the startup
and test program. York
Haven Generating Facility, York Haven, PA This
project scope was the upgrade of the 1926 hydroelectric generating facility.
Project included new electrical equipment and addition of automatic
control. Scope included replacement
of generator switchgear, main switchgear, 4 kV 115 kV step-up transformers,
station service switchgear, station service transformer, and updating the 115 kV
utility interconnection. Solar
Turbines, York, PA Project
was for the installation of 8 small combustion turbines at Caterpillar Tractor
substation. Responsibility was
utility project engineer working directly with Solar Turbines and their
engineering firm to specify protection requirements, review their protection and
control drawings, and make recommendations to allow them to meet the utility
requirements and to help them control the costs for interconnection.
Responsibility also included protective relay settings for the
interconnection, review generator and associated auxiliary protective relays,
and review of the final as built protection and control drawings. Combustion
Turbine Upgrade Project, Metropolitan Edison Co., PA This
project included the upgrading of the turbine and generator protection and
control schemes of eleven 20MW dual fuel fired combustion turbines.
Responsibility was protection and control engineer for the replacement of
the electro-mechanical generator and turbine control schemes with a PLC based
scheme. This included upgrading
automatic synchronizing schemes, frequency protection, voltage restrained
overcurrent protection, high and low voltage protection, loss of excitation
protection, and generator differential protection. Reliant
Energy Titus Station, Birdsboro, PA
Completed the design, installation, and testing to
upgrade the plant coal handling switchgear to handle a new coal blending system.
Performed short circuit and relay coordination studies for switchgear
relaying and the substation feeds to the switchgear. Ontelaunee
Energy Center, Temple, PA - Engineering
Manager for the installation of new 230-kV switching station for a 540 MW
natural gas fired generating facility owned by Calpine. AES
Ironwood Substation and Switchyard, Lebabon, PA
Engineering Manger for the design, installation,
and testing of a new 230kV utility substation and the owners 230kV switchyard.
The project also included splitting an existing 230kV transmission line
and relay upgrades at the remote terminals, including the addition of dual high
speed relaying schemes on the two lines formed from the split. AES
Red Oak Substation, Sayerville, NJ - Engineering
Manager for the installation of new 230-kV switching station for a 765 MW gas
fired generating facility owned by AES. Handsome
Lake Energy Center, Kennerdell, PA
- Engineering
Manager for the installation of new 345-kV switching station comprised of a (3)
breaker ring bus in support of the Handsome Lake Energy Project, a 250 MW gas
fueled power plant owned by Constellation Energy Group in Kennerdell, PA. Engineering
Studies Siegfried (USA), Pennsville, NJ -
Performed site electrical evaluation, composed single
line diagrams of their entire power distribution system, completed power system
modeling, load studies, short circuit studies, protective device coordination
review, and future planning studies. Completed an electrical
classification study of the plant facilities to properly classify all hazardous
locations per the NEC. INGENCO, Richmond, VA Completed
utility interconnection studies for two of their generation development
projects. Provided a report
including design requirements, single line diagrams, and protection requirements
that would be necessary to attach their generation to the utility grid. Programmable
Logic Controller (PLC) Applications Birdsboro 69 kV Restoration Scheme, Birdsboro, PA
- This scheme was designed to automatically reclose
three (3) 69 kV circuit breakers and a 13.2 kV transformer breaker upon an
operation of the adjacent transformer protection scheme. Stroudsburg 34.5 kV Circuit Breaker Transfer and LTC Control Scheme,
Stroudsburg, PA - This
scheme performed an automatic circuit breaker transfer between two (2) 34.5 kV
circuit breakers feeding a distribution substation.
Also incorporated into the design was an automatic LTC control for two
distribution power transformers in the substation. Lickdale Sectionalizing Scheme & 13.2 kV Tie Switch Scheme,
Lebanon, PA - This
installation included the sectionalizing scheme mentioned above and a 13.2 kV
tie switch scheme used to close two (2) 13.2 kV tie switches to pick up feeders
in the event of a transformer failure. Due
to the loading and characteristics of the feeders involved, the scheme also
performed an automatic change of relay settings on ABB DPU relays prior to
performing the transfer. Warren 115 kV Circuit Breaker & Relay Potential Transfer Scheme,
Warren, PA - This
scheme performed a bus transfer for two (2) 115 kV circuit breakers between two
isolated 115 kV busses. Prior to
performing the transfer, a successful transfer of relay potential needed to be
performed and verified. A 115 kV
reclosure scheme was also provided for one of the circuits. Erie South 230-115 kV Auto-transformer LTC Control Scheme, Erie, PA
- This scheme was installed to perform manual tap
changes for three (3) parallel 230-115 kV auto-transformers with different
numbers of LTC taps. PLC-based
RTU Projects Completed
PLC programming for ten (10) PLC-based SCADA RTU systems.
Programming of the PLC was completed utilizing IEC 1131 programming
language and included not only the development of the PLC resident software, but
also configuration and programming of various protocol converters utilized to
communicate with other intelligent electronic devices (relays and meters). Remote
Terminal Unit Standard, GPU Energy, Reading, PA
This project
included redesigning the control and data acquisition system platform at GPU
Energy to be able to provide the current control and analog data requirements
using communications systems and to be easily expandable to provide substation
automation with minimal wiring changes. This
project got national attention and was published in T&D magazine and
numerous presentations were given on this project.
|
|
a 2001 - Orion Technical Services, LLC |